reversive.Open planner ↗

Build a schedule backward.

When an opening date is fixed, work back from it to learn which commitments must start first. List handoffs and working days before setting dates.

Calculate a workback schedule

Start from the handover date

Choose the date the work must be ready. Reversive sets the last task to finish on the last working day before the deadline. If part of the work happens on deadline day, give the planner the day after as its cutoff.

Write down the handoffs

For a Friday, January 22, 2027 exhibit opening, installation needs both the printed panels and confirmed access to the venue. Confirming the venue can happen while the panels are in production. List those two prerequisites on the installation task.

TaskWork daysLatest startFinish
Approve exhibit copy3Jan 6Jan 8
Lay out wall panels2Jan 11Jan 12
Print and deliver4Jan 13Jan 18
Confirm venue access3Jan 14Jan 18
Install and light2Jan 19Jan 20
Walk the opening route1Jan 21Jan 21

This example skips weekends. If the team or supplier is closed January 18, mark that day blocked. Printing, venue confirmation and the work leading up to printing all have to move earlier. The timeline shows the closed day as a gap in any task spanning it.

Decide what to do when the start date is too late

If the team cannot start by January 6, enter its first available date. The planner shows the shortfall and marks the tasks that need to start earlier. If the deadline cannot move, check whether an approval can happen sooner, a task can be split into independent pieces, or the scope can change.

The darkest bars mark tasks that determine the latest feasible project start. A lighter bar has room to start earlier within the plan. That flexibility assumes separate tasks can run in parallel. If the same person must do two overlapping tasks, add the necessary dependency or reserve capacity in a separate plan.

Put the workback dates on a calendar

Download the plan as an .ics file. Entries use all-day dates without time zones. A task interrupted by a weekend or blocked date exports as separate blocks. Import into a separate calendar to compare the plan with other commitments. Recheck the export after dates change.

See also Microsoft’s guide to scheduling from a finish date and the iCalendar event specification.